Standard costing: problems with >1 product

Let's remember:

1.

Standard direct labour hours produced
=
(actual units produced) x (standard direct labour hours (sdlh)/unit)
=
the direct labour hours we should have used at the output level



2.

Flexible budget
(standard direct labour hours produced) x (€-rate for activity)
=
what we should spent on activity (direct labour hours or variable overhead)